Daily Report
Harborview Hotel — Sample Project
Eastwood Installations · June 14, 2026
Prepared by M. Rivera
Sanitized sample
Progress Today
Room 204 · 80%
Casegoods and headboard installed. Drawer hardware staged; awaiting replacement pulls before final sign-off.
Completed Areas
Floor 3 — Guest Rooms · 100%
Rooms 301–312 fully installed and cleaned. Ready for client walk-through.
Issues / Blockers
Room 204
Drawer pull hardware missing on nightstand. Holes drilled and ready; replacement hardware required.
Safety / Incidents
Protective floor covering in place throughout the work area. No incidents to report.
Deliveries Received
Received 14 cartons of casegoods and 6 headboards. Checked against packing list; no visible damage.
Notes
Lobby millwork complete and ready for final trim carpentry next visit.